PREFABRICATION REVIEW - SOUTHERN COURTYARD DEVELOPMENT : ADELAIDE CENTRAL SCHOOL OF ART, GLENSIDE
HIGH CUBE SHIPPING CONTAINERS READY FOR AUGEMENTATION AND PREFAB FITOUT.
CONTAINER SIDES CUT FOR LARGE SCALE SLIDING DOORS WITH NEW WALL BRACING FITTED
INTERNAL OF CONTAINERS WITH RAISED FLOOR AND INSULATED PANELS IN PLACE PRIOR TO PLYWOOD LININGS INSTALLED.
PAINTED CONTAINERS WITH ADDITIONAL NEW ROLLER ACCESS DOOR AND ELECTRICAL / LIGHTING FITMENTS READY FOR DELIVERY.
SHIPPING CONTAINERS CRANED INTO PLACE PRIOR TO BEING FIXED TO FOOTINGS ON SITE
MAIN CANOPY COLUMN FOOTING AND THREADED BOLTS PRIOR TO COLUMN AND BASEPLATE CONNECTION
MAIN CANOPY CLOUMNS IN PLACE, ROOF BEAMS CRANED INTO PLACE WITH HERITAGE FACADE BEYOND
STEEL PORTAL FRAMES AND LONG SPAN ARAMAX ROOF SHEETING
R12 FINISH CONCRETE SLAB POURED BETWEEN CONTAINERS FOR EXTERNAL TEACHING SPACE
FINAL TEACHING SPACE AS VIEWED FROM ABOVE